HOME

Hybrid Plant Technology

For

Distributed Power Generation

Dr. Michael Nakhamkin and Boris Potashnik, ESPC, Inc.

Ronald C. Hall and Dale T. Bradshaw, Tennessee Valley Authority

Dr. Robert Schainker, Electric Power Research Institute

Robert Moritz, Rolls Royce Allison

Ronald Wolk, Wolk Integrated Technical Services

Introduction

Based on number prognostications by leading authorities, electric power will be the fastest growing source of end-use energy throughout the world over the next two decades. Worldwide electricity usage is projected to grow to 23 trillion kWh in 2020, nearly doubling present demand. Bechtel Power estimates that the annual worldwide demand for distributed power generation (DG), including the combined heat and power generation (CHP) systems, will be on the order of 30 to 40 gigawatts over the next five years. Westinghouse estimates that 40 percent of all worldwide capacity addition from 1998 to 2008 will be DG of some form (Reference 1).

In the bulk of the power market, distributed energy technologies will find it difficult to compete with the nearly 60-percent-efficient combined-cycle plants as the design of choice for a power generation company, at least in the near or medium term. It should be expected, that the cost of electricity ($/kWh) produced at the place where power is generated by a small capacity DG plant, (which is less efficient and more expensive), should be higher compared to that produced by large power plants. DG plants are helped in this competition with large central station plants by various charges associated with the delivery of power from those plants such as a capacity charge ($/kW) for the power availability, transmission losses, distribution fees, etc. Also, sometimes DG economics are improved by the deferral of the construction of transmission lines.

DG plant economics are affected by the fact that a single power plant must typically meet a whole range of specific operating requirements, associated with power supply to a limited number of local customers. Specifics of a DG plant operation could be summarized as follows:

A single power generation unit performs :

Due to a singular consumer or limited number of consumers:

As a result, a typical DG plant is be sized to meet maximum (peak) power demands, but operates most of the time at 50% loads or lower with significantly reduced efficiency.

Currently available alternatives for small capacity DG plants are as follows:

This paper presents the novel Hybrid Concept (HC), which allows a single power plant to meet, in the most cost-effective manner, power supply requirements of a DG plant. This paper will concentrate on the explanations of the HC principles, description and availability of major components- CT-derivative plants and the compressed air storage vessels, typical HC operations, installed costs and economics.

The Hybrid Concept

The Hybrid Concept (the U.S. Patent #5,778,675) was invented by Dr. M. Nakhamkin of ESPC, with patent rights assigned to EPRI in accordance with a separate patent rights sharing agreement.

Figure 1a. Hybrid Concept Schematic

The basic HC plant consists of four major components and systems as shown in Figure 1a:

The major HC principles and the equipment selection specifics are as follows:

The alternative basic HC plant shown in Figure 1b differentiates from Figure 1a concept by the fact that the stored air is humidified before being injected into the CT. This concept (denoted as HCH) has two new components: the saturator for the air humidification with the hot water and the heat recovery unit for the water heating for the humidification process. The major idea behind this concept is that for the same peak power, the mass of the air stored could be significantly reduced due to humidification, thus reducing the storage size and costs, which is particularly critical for the above-ground storage. Also, the boost compressor size and costs are reduced. This concept is not particularly cost-sensitive to long hours of the storage.

 

 

  • Figure 1b. Hybrid Concept with Humidification Schematic

  • Combustion Turbine (or CT - derivative plants) for the Hybrid Concept

    The combustion turbine for the HC (HCH) application differs from any standard turbine by the following:

    The Rolls Royce Allison Company’s (RRA) KM7 combustion turbine model could be used practically without changes for the HC plants. RRA converted the KB7 into the KM7 model for a biomass application project, sponsored by DOE. The KM7 has provisions to take out the compressor discharge flow for external heating in a biomass burning FBC plant, and to inject the heated compressed air flow into the turbine. RRA’s personnel, jointly with ESPC, established that, while KM7 base load power is 4.77 MW, with the supplementary air from the storage, it could be increased to 7.9 MW for peak power generation.

    As mentioned before, for maximum peak power the compressor shall be separated from the expander with the installation of an automatic clutch. The separation of the compressor, to provide for the separately operating combustor/expander assembly, was also motivated by its application for a small capacity CAES plant – another power plant that is very promising for DG applications.

    The newly developed by RRA combustor/expander package is shown in Figure 2. It is comprised of a 501-KB7 turbine/combustor/diffuser configured with a 501 KC5S power turbine output shaft and exhaust system. The expander has the hot end drive and allows for direct inflow of air into the diffuser, eliminating a new radial inlet scroll design required for a front-end drive design. RRA performed required engineering work to establish the feasibility of this development and to estimate performance and costs.

  • Figure 2. Allison Turboexpander Module

  • Compressed Air Energy Storage System

    The compressed air storage is a major component of the HC plant. In order to meet a variety of site locations for DG plants, ESPC concentrated on storage in man-made buried vessels. These vessels are feasible and economical for the HC application, because only limited amounts of the supplementary air should be stored. An analysis of various potential compressed air storage containers, including steam-drum type pressure vessels, reinforced concrete pipes and various high pressure piping systems, resulted in the selection of the latter. The system consists of buried pipe, designed and fabricated to the U.S. DOT Transportation Pipeline Safety Standards. The precedence for pipeline air storage is the natural gas transmission lines throughout the U.S. Pipeline, with a 48-inch diameter and maximum pressure of approximately 1550 p.s.i.a was selected as the storage facility for the hybrid plant. Due to higher allowable stresses, based on the aforementioned standards, engineering and cost estimation efforts resulted in the conclusion that the air storage system can be installed for approximately $30/kW per hour of storage. For the HCH plant with 60% of the injected air humidification (which is easily achieved), this cost could be reduced to $10/kW per hour of storage.

    Hybrid Concept Operations

    Flow path diagrams and performance characteristics for various HC plant operations are presented in Figures 3 through 8. For simplicity reasons, the operations are explained for the HC plant based on RRA’s KC5S simple cycle CT, which includes the aforementioned combustor/expander package and the compressor connected via a clutch.

  • Figure 3 through Figure 8. Hybrid Concept Operating Modes

  • There are five modes of HC plant operations:

    Hybrid Concepts with CHAT and Combined Cycle Plants

    As it was mentioned above, the hybrid concept could be based on any combustion turbine derivative plant, which is able to utilize the hybrid concept’s major feature – supplementing the compressed air flow during peak hours with the compressed air stored during off-peak hours. Figures 9 and 10 show the flow path and performance characteristics of HC plants based on the CHAT and CC plants, respectively. The net power and heat rates at base and peak loads are indicated, as well as the required off-peak power during recharging, and the time needed to recharge after 3 hours of maximum peaking operation.

    As it is evident from Figures 9 and 10, these two concepts are much more efficient, and, though more complicated in operations and maintenance are preferable for locations with high projected fuel costs and significant base-load operating hours.

  • Figure 9 and 10. Hybrid CHAT and Combined Cycle Concept Schematics

  • Hybrid Concept Plant Costs

    ESPC and its contractors conducted rather detailed cost estimates for various HC and HCH configurations. Capital costs are based upon a combination of manufacturer quotations, adjustments to previous equipment quotes for other projects, and in-house installation costs for projects of similar size and scope. Total plant specific capital costs ($/kW) are based upon the maximum peak output rating of HC plants, all based on the RRA’s combustor expander package and on three hours of the storage or three continuous peak generation hours. Estimated costs are as follows:

    As it was stated above the HCH plant will not be significantly affected by additional storage hours. As anticipated, the simplest Hybrid CT (though less base-load efficient) has the lowest specific capital cost due to both the simplicity of the cycle and the largest peak/base ratio. Conversely, the most efficient CHAT hybrid has the highest specific cost primarily due to its lowest peak/base ratio.

     

    Comparative Analysis of Economics of Hybrid Concepts with Other DG Alternatives

    Table 1 presents a comparative economics of three potential alternative DG plants:

    The comparative analysis was performed based on the following assumptions:

     

    Table 1

    Comparative Analysis of Hybrid-CT vs. Two CT Alternatives

     

    Hybrid CT based on

    Simple Cycle

    Simple Cycle

     

    Allison KC7 CT

    (15 MW CT)

    (2 x 7.5 MW CTs)

    Peak Load Net Power, MW

    15.94

    15.94

    15.78

    Peak Load Net Heat Rate, Btu/kWh (LHV)

    4,030

    11,690

    11,690

    Peak Load Hours per Day, hours

    3

    3

    3

    Charging Hours per Day, hours

    4

    0

    0

    Base Load Power, MW

    4.815

    4.815

    4.815

    Base Load Net Heat Rate, Btu/kWh (LHV)

    11,690

    16,900

    12,700

    Base Load Hours per Day, hours

    17

    17

    17

    Specific Capital Cost, $/kW

    430

    500

    600

    Fuel Cost, $/kWh

    0.027

    0.045

    0.037

    Off-Peak Energy, $/kWh

    0.004

    0.000

    0.000

    Total Cost of Electricity, $/kWh

    0.0532

    0.0707

    0.0669

    Table 1 is self-explanatory. It shows that for assumed DG plant operations and economic factors, the HC has both the lowest specific costs ($/kW) and the lowest cost of electricity ($/kWh) as compared to two alternative CT plants (selected for the same power generation requirements). Key factors contributing to the HC plant better economics are built up in the very essence of the HC:

    It was demonstrated that for assumed DG plant operations and economic factors, the HC based on the CHAT plant has both the lowest specific costs ($/kW) and the lowest cost of electricity ($/kWh) as compared to the CHAT plant selected for the same duties.

    Similar results could be demonstrated for HC plants with the utilization of a CC plant as a CT-derivative plant.

    Summary of Hybrid Plant Operation and Benefits

    Extensive engineering and economic studies resulted in the following conclusions:

    1. The Hybrid Concept for DG is expected to be more economical, as compared to any other evaluated alternative.
    2. The advantages of the Hybrid Concept are embedded in its essential principles and could be explained as follows;
    1. Rolls Royce Allison developed the following combustion turbine models which could be easily applicable for the HC plants:
    1. The compressed air storage capacity is a relatively small, due to small plant unit sizes (5 MW – 30 MW) and very short peak power duration (1-2 hrs/day). Therefore, it could utilize man-made storage vessels, vs. conventionally used underground formations for CAES plants. ESPC developed the compressed air storage concept allowing placement of the HC without any site restrictions. The concept is based on the storage facility based on buried HP with specific storage costs of approximately $30/kW per hour of storage for HC plant and $10/kW for the HCH concept.
    2. For underground storage (if available) specific costs of storage could be significantly lower.

    References

    1. "Small Generators Fuel Big Expectations," Power Engineering. February 1999.
    2. "CHAT Technology at 54.7% Efficiency, Ready for Commercial Demo," Gas Turbine World. May-June 1996.
    3. "12-MW demo plant proposed to prove out CHAT technology", Gas turbine World, May-June, 1999.
    4. US Patent # 5,778,675 "Method of Power Generation and Load Management with Hybrid Mode of Operation of a Combustion Turbine Derivative Power Plant, Dr. Michael Nakhamkin, Inventor. July 14, 1998.
    Back to Top
    HOME